Slabs poured…

The three slabs were all poured today and look great. A slight shower shortly after pouring, but never rained to hard and will not impact finish. Beach and shallow end slabs can be see in the photo below, with the bubblers and drains visible (drains under blocks!) The following photo…

Continue reading

Slabs ready for pour…

The three slabs are now ready for the concrete pour tomorrow. Following photo shows the bubblers in what will be the beach (plage) area. The next photo shows the beach and shallow end, with the shallow end drains being set level in ready-mix concrete, ahead of the pouring of the…

Continue reading

Terrace work update…

Raised terraces are now complete, with the exception of the tiles which will be done at a later date, along with the pool deck level patio. The steps rise up to a higher level terrace, with dinning area in the middle, which will be enclosed with a glass balustrade. Currently…

Continue reading

More progress on terrace…

Some more photos showing the progress being made by the team on the terracing. There are now five courses of blocks installed, so I now assume the ring beam will be the next to be installed, which will also be used to tie into the slabs.

Continue reading

Terrace Blockwork…

More photos as the blockwork progresses on training walls for the terracing area around the pool. The photo below shows the ‘planter’ at the far end of the run of blocks which will adjoin the steps from the top terrace down to the pool level. The following photo shows what…

Continue reading