Technical room ready

On the previous trip we had installed a temporary roof on the technical room to allow the electrician to connect up the fuse box with the mains. However, I have actually got back out before that has been done and have completed the final roof, as seen in the following…

Continue reading

Plumbing finished…

Well nearly… The pipes from the pool and into the technical room have now been connected and the remainder of the plumbing within the technical room completed. This work included the installation of the other two pumps and the filter cartridge unit. We opted for a cartridge system, as we…

Continue reading

Pool slab poured…

The biggest concrete pour of the build, with 14 cubic metres being poured using the long reach pump truck (28m arm). My daughter is tamping the concrete with the 2m metal bar to help bring the ‘cream’ to the top and sink any aggregate, leaving a nice smooth finish. The…

Continue reading

Filling time…

Apart from adding additional support to the feature wall formwork, following the disaster on Monday, we have been busy getting the slab ready for pouring next week. My daughter has been busy laying membrane and then we have fitted the drains at the correct heights. S-Shaped spacers set the height…

Continue reading