All done for this trip…

With the school holiday coming to an end soon and the news that the concrete plant is now on a two week shut-down, that about completes the work that we can do for this trip. We will need to come back out soon, as we do not want to leave…

Continue reading

Feature wall started…

The suspended beam has now been started. The beam spans the width of the pool, under which a 100mm gap exists for the roller shutter to come through, a little like a letter box. Given that it is a suspended beam, spanning 4.5m, we got a structural engineer to do…

Continue reading

Backfilling for pool terrace…

52 tonnes of hardcore was delivered to backfill around the pool to bring the level of the pool terrace up to required height. Thankfully we have mechanical assistance and the hand to eye co-ordination of a teenager! PVC drains have been laid within the hardcore, which will take the water…

Continue reading