Second layer installed

The second layer of reinforced steel mesh has now been laid. It is at this point that we realise why the full size ST25C would have been useful. We have to place two sheets per width, which means that in some places we have four sheets overlapping, causing potential high…

Continue reading

Formwork set

The formwork has now been setup, which was a little bit of a hassle as the boards are not as specified. They range from 175mm to 190mm in height, with none of them being 200mm as per specification. However, after some effort, they have been setout to give a level…

Continue reading

Construction begins…

It was a busy morning this morning, with the delivery of the necessary materials to do Phase One (concrete slab). The delivery included a 200 x 8mm steel reinforcing bars, 34 sheets of ST25CS steel reinforcing mesh (3m x 2.4m of 7mm rebar in 15×15 mesh), 150 L-Shaped 10mm rebar,…

Continue reading

Today we hit rock bottom

Today saw the first major landmark in this project, with the whole for the main pool basin being dug. The hole is approximately 10m long, 5.5m wide, and 1.7m deep. It proved to be a little harder work that first expected and needed a much smaller bucket to get through…

Continue reading

Setting out

We are now back in France and have setout the the various elements of the pool and terraces. The yellow line in the right hand third is where the top terrace will end and the steps down to the pool deck begin. You can see the pool excavation area marked…

Continue reading