Formwork set

The formwork has now been setup, which was a little bit of a hassle as the boards are not as specified. They range from 175mm to 190mm in height, with none of them being 200mm as per specification.

However, after some effort, they have been setout to give a level top to work from, albeit some backfilling around the bottom will be required in places to make sure that we do not have any leaks in the self-placing concrete when it is poured.