Formwork set

The formwork has now been setup, which was a little bit of a hassle as the boards are not as specified. They range from 175mm to 190mm in height, with none of them being 200mm as per specification. However, after some effort, they have been setout to give a level…

Continue reading

Construction begins…

It was a busy morning this morning, with the delivery of the necessary materials to do Phase One (concrete slab). The delivery included a 200 x 8mm steel reinforcing bars, 34 sheets of ST25CS steel reinforcing mesh (3m x 2.4m of 7mm rebar in 15×15 mesh), 150 L-Shaped 10mm rebar,…